The project includes utility supply channels, starting from the boiler room (Building D.11) and extending to the planned radiotherapy center (formerly C.10). The works that are foreseen are:
- Reinforced concrete Infrastructure/service structures
- Excavation works for utilities;
- Excavation works for electricity supply systems;
- Reinforced concrete structures (supply channels for power lines / services)
- Re-planning and reorganization of combined sewers;
- Dismantling of the water supply network, realization of temporary connections with buildings and re-planning of new water supply lines;
- Conversion of gas supply network;
- Excavation works for the whole cable system (temporary configurations and their final extension);
- Excavation protection;
- Removal of vegetation (paths, garden landscapes, etc.);
Restore the landscape to its original state using a coating layer, as the alignment and plan of the lines will change